Rate of tax (service)— In the instant case, the applicant is engaged in executing works contract to Indian Railways such as construction of Rail under bridge, construction of tunnels and supplying and stacking of ballast, earth work and also sub contract of all the mentioned works.
The applicant has sought advance ruling in respect of the following questions:-
i. What percentage of GST output tax should be charged for our nature of works contract executed to Indian Railways.
a) On Railway under Bridge works
b) Construction of Tunnels for Railways
c) Supply and stacking of ballast
d) Execution of Earth Works Contract
e) Subcontract works for the above mentioned contract works
The applicant has stated that they are engaged in supply of works contract services to Indian Railways such as construction of Rail under bridge, construction of tunnels, execution of Earth Works Contract, supply and stacking of ballast and sub-contract of the above-mentioned contract works and wants to know the rate of GST on the same.
Held that— i. Works contract services like
a) construction of Railway under Bridge executed to Indian Railways by the Applicant is exigible to GST at 18% (SGST @ 9% and CGST @ 9%) if the Applicant is providing the services either as a main contractor or as a sub-contractor to main contractor.
b) construction of Tunnels executed to Indian Railways by the Applicant is exigible to GST at 18% (SGST @ 9% and CGST @ 9%) if the Applicant is providing the services either as a main contractor or as a sub-contractor to main contractor.
ii. Works contract services involving predominantly earth work (that is, constituting more than 75per cent, of the value of the works contract) executed to Indian Railways (Central Government) by the Applicant is exigible to GST at 12%(SGST @ 6% and CGST @ 6%) if the Applicant is providing the services either as a main contractor or as a sub-contractor to main contractor.
iii. Supply of ballast to railways is exigible to GST at 5%(CGST @ 2.5% and SGST @2.5%) (HSN 2517) as per entry No. 126 of Schedule I of Notification No. 1/2017-Central Tax (Rate), dated: 28.06.2017