Levy of GST— The subject appeal has been filed against the Order passed by the Telangana State Authority for Advance Ruling.
In the instant case, the applicant is engaged in production and distribution of electricity obtained from solar energy. They have engaged M/s. Belectric India (P) Ltd for construction of solar power project. The agreement has clauses for recovery of liquidated damages on (2) counts, one delay in delivering of the contract and the other regarding non-performance of the plant. The applicant is desirous of ascertaining exigibility of liquidated damages to GST on account of delay in commissioning and its time of supply.
Question had raised for advance ruling are as follows—
1. Whether liquidated damages recoverable by the applicant from Belectric India on account of delay in commissioning, qualify as a ‘supply’ under the GST law, thereby attracting the levy of GST?
2. If the answer to Question No. 1 is in the affirmative, what should be the time of supply when liability to pay GST is triggered?
The lower authority ruled that liquidated damages recoverable by the applicant from Belectric India on account of delay in commissioning, qualify as a ‘supply’ under the GST law, and thereby attracting the levy of GST. The date on which the liquidated damage is determined as per the formula prescribed in the clause 6 of the contract is the time of supply of service entry in 5(e) of Schedule II by the applicant.
Aggrieved by the above ruling, the present appeal has been file by the appellant on the following grounds—
1. The impugned order is a non-speaking order and is liable to be set aside
2. Statement containing the Appellant’s interpretation of law and/or facts, as the case may be, in respect of the aforesaid question(s)
The CBIC has issued Circular No. 178/10/2022-GSTdated:3.8.2022 related to GST applicability on liquidated damages. As per para 7.1.6 of the said circular, it was, interalia, observed that when principal supply is exempt, the ancillary activities to such principal supply would not get attracted to GST. Since in the present case, the applicant’s principal supply is production and distribution of electricity, which is exempt from payment of GST, the liquidated damages received by the applicant towards such supply need to be considered as flow of money without having implication of GST payment.
As per the circular where the amount paid as ‘liquidated damages’ is an amount paid only to compensate for injury, loss or damage suffered by the aggrieved party due to breach of the contract and there is no agreement, express or implied, by the aggrieved party receiving the liquidated damages, to do or abstain from doing anything for the party paying the liquidated damages, in such cases liquidated damages are mere a flow of money from the party who causes breach of the contract to the party who suffers loss or damage due to such breach. Such payments do not constitute consideration for a supply and are not taxable.
Held that— liquidated damages recoverable by the applicant from Bi-electric India on account of delay in commissioning, does not qualify as a ‘supply’ under the GST law.